%T Managing the 'receding edge' %A Camille Salem %A Cecile Lefevre %A Jun Li %A et al. %I 26th Annual Conference of the International Group for Lean Construction (IGLC), 18-22 July 2018, Chennai, India %D 2018 %K Design, %K Construction industry %P 713-723 %R 10.24928/2018/0414 %U https://apo.org.au/node/304740 %V 2 %X So much attention is paid to starting construction activities, and starting new work at regular time intervals to a beat (aka. takt) that, not surprisingly, work to finish those very activities may fall behind. This paper focuses, not on the start-, the leading edge, but on the end of activities, the receding edge. The receding edge articulates when work is done-done and the successor contractor may start their work, unimpeded by their predecessors' unfinished work or 'leftovers' (e.g., areas left dirty and cluttered with remnants). %9 Conference paper