TY - Conference paper AU - Camille Salem AU - Cecile Lefevre AU - Jun Li AU - et al. PY - 2018 T1 - Managing the 'receding edge' PB - 26th Annual Conference of the International Group for Lean Construction (IGLC), 18-22 July 2018, Chennai, India DO - https://doi.org/APO-304740 UR - https://apo.org.au/node/304740 VL - 2 AB - So much attention is paid to starting construction activities, and starting new work at regular time intervals to a beat (aka. takt) that, not surprisingly, work to finish those very activities may fall behind. This paper focuses, not on the start-, the leading edge, but on the end of activities, the receding edge. The receding edge articulates when work is done-done and the successor contractor may start their work, unimpeded by their predecessors' unfinished work or 'leftovers' (e.g., areas left dirty and cluttered with remnants). ER -